Question: Question 2 8 2 pts The for the entire project or each work package provides a baseline against which actual cost and work performance can
Question
pts
The for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project.
cumulative actual cost CAC
cumulative budgeted cost CBC
cumulative earned value CEV
total budgeted cost TBC