Question: The _ _ _ _ for the entire project or each work package provides a baseline against which actual cost and work performance can be
The for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project.
a
contract cumulating amount
b
cumulative budgeted cost
c
total cumulative fees
d
total budgeted cost