Question: The ____ for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any
The ____ for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project.
|
| a. | cumulative budgeted cost |
|
| b. | total cumulative fees |
|
| c. | total budgeted cost |
|
| d. | contract cumulating amount |
The cumulative budgeted cost is
|
| a. | the committed costs for an activity. |
|
| b. | the amount budgeted to accomplish the work scheduled to a point in time in the project. |
|
| c. | the aggregate estimated costs of all the activities. |
|
| d. | the sum of all the funds expended to a point in time in the project. |
The cumulative earned value of the project is
|
| a. | the sum of the differences between what was planned and the actual costs. |
|
| b. | the sum of the budgeted costs of the work actually performed. |
|
| c. | the sum of the planned costs of the project |
|
| d. | the sum of the budgeted cost of the work scheduled. |