Question: Question 2 8 The AOA network for a certain project is given in the graph below with the task durations ( in days ) in

Question 28
The AOA network for a certain project is given in the graph below with the task durations (in days) in the table beneath it. The activities d1 and d2 are dummy activities.
What activities are on the critical path?
\table[[Activity,b,c,d,e,f,g,h],[Duration,8,14,9,6,10,8,1]]