Question: QUESTION 2 A software project has the following activities together with their durations: Activity Preceding Activity Duration (months) A - 4 B - 3 C
QUESTION 2
A software project has the following activities together with their durations:
| Activity | Preceding Activity | Duration (months) |
| A | - | 4 |
| B | - | 3 |
| C | A | 6 |
| D | A | 5 |
| E | A,B | 3 |
| F | D,E | 3 |
| G | A,B | 7 |
| H | C,F | 6 |
| I | C,F,G | 8 |
| J | H,I | 10 |
(a) Draw a network diagram for the above project. (13 marks)
(b) Determine the critical path and the overall project completion time. (2 marks)
(c) Tabulate the above project with columns of EST, EFT, LST, LFT and TF. (10 marks) (Total: 25 marks)
Thanks in regards, charts or handdrawn answers are appreciated.