Question: Question 2 Given the project within the table below, calculate the following: The critical path 1 b. The minimum project duration a. a. a. c.

Question 2 Given the project within the table

Question 2 Given the project within the table below, calculate the following: The critical path 1 b. The minimum project duration a. a. a. c. The amount of slack for each activity Activity A Duration (hours) 4 B 3 10 Immediate Predecessors None None None B,C D D 7 1 1 F G 5 A,F