Question: Question 21) Given the project within the table below, calculate the following: a. Draw Network diagram b. The critical path c. The minimum project duration

Question 21) Given the project within the table
Question 21) Given the project within the table below, calculate the following: a. Draw Network diagram b. The critical path c. The minimum project duration d. The amount of slack for each activity Activity Duration (hours) 42 3e 102 Be ce Immediate Predecessors None le None None le B.Celle De Ee le A Fe le Ee le le

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts