Question: (1 ) a. Given the project within the table below, calculate the following: The critical path b. Project completion time The amount of slack for

(1 ) a. Given the project within the table below,

(1 ) a. Given the project within the table below, calculate the following: The critical path b. Project completion time The amount of slack for each activity d. Draw the network c. Task Predecessor(s) Time (Minutes) 3 A B 5 9 A D 6 . AL E 4 F 8 G 12 D,E,F H 5 G