Question: QUESTION 2 The optimistic time for a certain task is 4 days, while its most likely time is 7 days and its pessimistic time is

QUESTION 2 The optimistic time for a certain task

QUESTION 2 The optimistic time for a certain task is 4 days, while its most likely time is 7 days and its pessimistic time is 14 days. When using the PERT technique, which of the following is closest to the expected time for this task? a. 2.78 days O b. 14.00 days O c. 7.00 days O d. 7.67 days O e. 8.33 days