Question: Project task E has the following estimates: ( 1 ) optimistic time 1 0 days, ( 2 ) Pessimistic time - 2 0 days, and

Project task E has the following estimates: (1) optimistic time 10 days, (2) Pessimistic time -20 days, and (3) Most likely time 12 Days. What is the expected time (.2 pt) and standard deviation (.2 pt) of task E? Show all your work.