Question: Project task E has the following estimates: ( 1 ) optimistic time 1 0 days, ( 2 ) Pessimistic time - 2 0 days, and
Project task E has the following estimates: optimistic time days, Pessimistic time days, and Most likely time Days. What is the expected time pt and standard deviation pt of task E Show all your work.