Question: Question 2 (This question is similar to Problem Set 1 that you completed) On a blank page, draw the project network diagram for the table

Question 2 (This question is similar to Problem
Question 2 (This question is similar to Problem Set 1 that you completed) On a blank page, draw the project network diagram for the table below. Then, show the ES, EF, LF, LS, and Slack for each task. Task Time (days) A B D E F 50 20 5 35 30 Immediate Predecessor(s) None None A, B D, E 25 Solve this question on a blank page, take a picture of your solution, and insert (copy- paste) the picture in the space below. If you are not sure how to insert the picture, you may submit the picture as a separate file along with this Word file