Question: Question 2 : Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost
Question : Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $ and there is a savings of $ per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. What is the optimum costtime schedule for the project?
Note: The correct normal project duration and total direct cost are provided. Show ALL of your working to get the points
tableActtableCrash CostSlopetableMaximumCrash TimetableNormalTimetableNormalCostABCDEFGH
Project duration
Direct cost
Indirect cost
Total cost
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
