Question: Question 2 . You have collected the data for a process. The activity time is given below. (a) Construct a flow chart based on the

Question 2. You have collected the data for a process. The activity time is given below.

Question 2 . You have collected the data for a

(a) Construct a flow chart based on the information in the table. For each activity, report the earliest start, earliest finish, latest start, latest finish times, and the slack time on the diagram using Forward scheduling and Backward scheduling. Report the process flow time and critical path.

(b) According to the flow chart you draw in (a), if Activity D is delayed by 1 minute, then what will happen to the process flow time (increase, decrease or unchanged)?

(c) You want to reduce (or shorten) the process flow time by 1 minute. According to the diagram you draw in (a), what are the possible options? (Provide at least two options.)

Activity A B Activity time (Minutes) 2 Immediate Predecessors None A B 3 4 D 5 B Cand D E 3 F E 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!