Question: You have collected the data for a process. The activity information is given below. Activity | Immediate Activity Possible Crash Predecessors time Crash Time Cost

You have collected the data for a process. The activity information is given below. Activity | Immediate Activity Possible Crash Predecessors time Crash Time Cost Per (Days) (Days) Day o | 57,000 A z s200 2 $100 5 A o s e o T |oadE |2 (a) Construct a flow chart based on the information in the table. For each activity, time on the diagram using Forward pass and Backward pass. Report the process flow time (i.e., project completion time) and critical path(s). (b) According to the flow chart you draw in (a), if Activity B is delayed by 1 day, then what will happen to the process flow time (increase, decrease or unchanged)? () You want to reduce (or shorten) the process flow time by 1 day, which activity should be crashed to minimize the cost