Question: You have collected the data for a process. The activity time is given below. Activity, Immediate Predecessors, Activity time ( Days ) , Possible Crash
You have collected the data for a process. The activity time is given below.
Activity, Immediate Predecessors, Activity time Days Possible Crash Time Days Crash Cost Per Day
A None, $
B A $
C B
D B $
E C and D $
F E $
a Construct a flow chart based on the information in the table. For each activity, report the earliest start, earliest finish, latest start, latest finish times, and the slack time on the diagram using Forward pass and Backward pass. Report the process flow time ie project completion time and critical paths
b According to the flow chart you draw in a if Activity B is delayed by day, then what will happen to the process flow time increase decrease or unchanged
c You want to reduce or shorten the process flow time by day, which activity should be crashed to minimize the cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock