Question: Question 20 (1 point) An activity on a PERT network has the following time estimates: optimistic = 8, most likely = 12, and pessimistic =

Question 20 (1 point) An activity on a PERT

Question 20 (1 point) An activity on a PERT network has the following time estimates: optimistic = 8, most likely = 12, and pessimistic = 28. Its expected time is (please round off to two decimal digits) Your Answer: Your Answer Question 21 (1 point) An activity on a PERT network has the following time estimates: optimistic = 9, most likely = 19, and pessimistic = 21. Its variance is (please round off to two decimal digits) Your Answer: Your