Question: Question 21 A project's BAC is $60,000. Its EV is $53,000. The AC is $55,000, the CPI is 0.97, and the SPI is 1.23. The
Question 21
A project's BAC is $60,000. Its EV is $53,000. The AC is $55,000, the CPI is 0.97, and the SPI is 1.23. The bottom-up ETC is $6,000. Calculate this project's EAC based on its cost performance so far.
Select one:
a. $61,000
b. $61,855.67
c. $60,882.35
d. $62,000
Question 23
Which elements are inputs to the control cost process?
Select one or more:
a. Change requests
b. Organizational process assets
c. Project documents
d. Work performance data
e. Cost forecasts
f. Project management plan
g. Project funding requirements
Question 24
What elements are inputs to the estimate costs process?
Select one or more:
a. Project schedule
b. Cost management plan
c. Resource requirements
d. Requirements documentation from past projects
e. Scope baseline
f. Activity list templates from past projects