Question 21

A project's BAC is $60,000. Its EV is $53,000. The AC is $55,000, the CPI is 0.97, and the SPI is 1.23. The bottom-up ETC is $6,000. Calculate this project's EAC based on its cost performance so far.

Select one:

a. $61,000

b. $61,855.67

c. $60,882.35

d. $62,000

Question 23

Which elements are inputs to the control cost process?

Select one or more:

a. Change requests

b. Organizational process assets

c. Project documents

d. Work performance data

e. Cost forecasts

f. Project management plan

g. Project funding requirements

Question 24

What elements are inputs to the estimate costs process?

Select one or more:

a. Project schedule

b. Cost management plan

c. Resource requirements

d. Requirements documentation from past projects

e. Scope baseline

f. Activity list templates from past projects

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!