Question: Question 22 Not yet A project has four major activities Activity A precedes activity B, activity C precedes activity D. 3. point estimates for activities

Question 22 Not yet A project has four major
Question 22 Not yet A project has four major activities Activity A precedes activity B, activity C precedes activity D. 3. point estimates for activities are A(3.5, 7. 10.5), B( 2.5, 5, 75), C(1.5,3,45), D( 4.5, 9.135) weeks. What probability would you assign to a project duration of more than 12 weeks? answered Marked out of 2.00 - Flag question O a 0.261 Ob 0.5 OC 0.75 Od 0.656