Question: Question 22. What is the project duration (days) ? Question 22. How much is the slack for path ACEFGI ? Show calculation Question 23. A,

| Question 22. | What is the project duration (days) ? |
| Question 22. | How much is the slack for path ACEFGI ? Show calculation |
| Question 23. | A, C, F and I and I can't be crashed |
| Each of the other activities can be crashed by 3 days | |
| 2 points | |
| What is the shortest project duration possible? |