Question: The following table provides the information necessary to construct a project network diagram and project crash data: Crash the project until no more crash can

The following table provides the information necessary to construct a project network diagram and project crash data:

  1. Crash the project until no more crash can be performed
  2. How much it would cost
  3. The new critical path(s)

Activity

Immediate predecessor

Activity Time (weeks)

Activity Cost ($)

Normal

Crash

Normal

Crash

A

--

16

8

2000

4400

B

--

14

9

1000

1800

C

A

8

6

500

700

D

A

5

4

600

1300

E

B

4

2

1500

3000

F

B

6

4

800

1600

G

C

10

7

3000

4500

H

D, E

15

10

5000

8000

End

F, G, H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!