Question: The following table provides the information necessary to construct a project network diagram and project crash data: Crash the project until no more crash can
The following table provides the information necessary to construct a project network diagram and project crash data:
- Crash the project until no more crash can be performed
- How much it would cost
- The new critical path(s)
| Activity | Immediate predecessor | Activity Time (weeks) | Activity Cost ($) | ||
| Normal | Crash | Normal | Crash | ||
| A | -- | 16 | 8 | 2000 | 4400 |
| B | -- | 14 | 9 | 1000 | 1800 |
| C | A | 8 | 6 | 500 | 700 |
| D | A | 5 | 4 | 600 | 1300 |
| E | B | 4 | 2 | 1500 | 3000 |
| F | B | 6 | 4 | 800 | 1600 |
| G | C | 10 | 7 | 3000 | 4500 |
| H | D, E | 15 | 10 | 5000 | 8000 |
| End | F, G, H |
| |||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock