Question: Question 23 1 pts What is a work breakdown structure? O A list of the activities making up the higher levels of the project O

Question 23 1 pts What is a work breakdown

Question 23 1 pts What is a work breakdown structure? O A list of the activities making up the higher levels of the project O A definition of the hierarchy of project tasks, subtasks, and work packages O A Gantt chart O A depiction of the activities making up a project Question 24 1 pts Project Management. A simple project listing of four activities, their predecessors and their durations are presented here: Activity Immediate Predecessor Duration (Days) A None 10 | A 5 A 11 D B, C 5 What is the duration of the entire project? O 25