Question: Question 24 (4 points) Saved What is the name for the sequence of activities that determines total project completion time? The Crash Time Predecessor Activities

Question 24 (4 points) Saved What is the name for

Question 24 (4 points) Saved What is the name for the sequence of activities that determines total project completion time? The Crash Time Predecessor Activities The Critical Path Network Diagram