Question: Question 24 Earliest start time (ES) is the earliest time at which a specific activity can begin O A calculated on the basis of the

Question 24 Earliest start time (ES) is the earliest time at which a specific activity can begin O A calculated on the basis of the project estimated start time and the estimated durations of preceding activities B.calculated on the basis of the project estimated finish time and the estimated durations of preceding activities. C calculated on the basis of the project estimated start time and the estimated durations of succeeding activities D.calculated on the basis of the project estimated start time and the estimated durations of approaching activities
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
