Question: Find the project duration & critical path: Activity Duration(Weeks) Immediate Predecessors A 10 B 4 - C 6 - D 4 B E 1 C,
Find the project duration & critical path: Activity Duration(Weeks) Immediate Predecessors A 10 B 4 - C 6 - D 4 B E 1 C, D F 4 C G 4 A, D H 5 E, F Project Schedule PATH DURATION A-G 10+4=14 weeks B-D-G 4+4+4=12 weeks B-D-E-H 4+4+1+5=14 weeks C-E-H 6+1+5=12 weeks C-F-H 6+4+5=15 weeks Q 1. If C-F-H is the critical path at 15 weeks. Using the network diagram and project schedule that you created. Identify what the Earliest Start Time (ES) would be for Activity "G" Q 2. Using the network diagram and project schedule that you created. Identify what the Earliest Start Time (ES) would be for Activity "E" Q 3. Using the network diagram and project schedule that you created. Determine what is the latest finish time for Activity - "G"? a. 10 b. 11 c. 14 d. 15