Question: QUESTION 26 PROBLEM E: The following table contains information about a project. Use it to answer the problems 26 - 27: The Project Manager is
QUESTION 26
PROBLEM E:
The following table contains information about a project. Use it to answer the problems 26 - 27:
The Project Manager is about to begin a project comprised of the following six activities:
TIME ESTIMATES (DAYS)
| Activity | Immediate Predecessor(s) | Optimistic | Most Likely | Pessimistic |
| J | -- | 8 | 10 | 15 |
| K | -- | 7 | 8 | 9 |
| L | J | 5 | 6 | 10 |
| M | J | 3 | 3 | 3 |
| N | K,M | 1 | 5 | 9 |
| O | K,M | 4 | 7 | 10 |
| P | L,N | 3 | 8 | 10 |
26. What is the expected (mean) time for project completion?
| a. 23 days | ||
| b. 66 days | ||
| c. 31 days | ||
| d. 26 days | ||
| e. 47 days |
5 points
QUESTION 27
What is the probability that the completion time for this project will be greater than 28 days?
| a. 0.8264 | ||
| b. 0.1736 | ||
| c. 0.7544 | ||
| d. 0.6772 | ||
| e. 0.4987 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts