Question: The following table contains information about a project. Use it to answer the problems 2 6 - 2 7 : The Project Manager is about

The following table contains information about a project. Use it to answer the problems 26-27 : The Project Manager is about to begin a project comprised of the following six activities:
TIME ESTIMATES (days)
\table[[,Immediate,,,],[Activity,Predecessor(s),Optimistic,Most Likely,Pessimistic],[J,-,8,10,15],[K,-,7,8,9],[L,J,5,6,10],[M,J,3,3,3],[N,K,M,1,5,9],[O,K,M,4,7,10],[P,L,N,3,8,10]]
What is the expected (mean) time for project completion?
a.23 days
b.66 days
c.31 days
d.26 days
e.47 days