Question: QUESTION 28 Problem C: Use the following to answer questions 28-29: A quality analyst wants to construct control charts for controlling a packaging process. Each
QUESTION 28
Problem C: Use the following to answer questions 28-29:
A quality analyst wants to construct control charts for controlling a packaging process. Each day last week, he randomly selected four packages and weighed them. The data from that activity appears below.
|
| Weight |
| |||
| Day | Monday | Tuesday | Wednesday | Thursday | Friday |
| Package 1 | 23 | 23 | 21 | 18 | 22 |
| Package 2 | 22 | 21 | 19 | 20 | 17 |
| Package 3 | 24 | 21 | 20 | 20 | 22 |
| Package 4 | 23 | 19 | 20 | 19 | 20 |
The upper and lower control limits for the means are:
| A) UCL = 22.64; LCL = 18.56 | ||
| B) UCL = 22.88; LCL = 18.51 | ||
| C) UCL = 23.033; LCL = 18.367 | ||
| D) UCL = 21.0; LCL = 17.0 | ||
| E) UCL = 22.98; LCL = 18.02 |
QUESTION 29
The upper and lower control limits for the Range are:
| A) UCL = 6.846; LCL = 0 | ||
| B) UCL = 7.25; LCL = -5.2 | ||
| C) UCL = 7.759; LCL = 0 | ||
| D) UCL = 6.389; LCL = 0.0 | ||
| E) UCL = 7.302; LCL = 0 |