Question: The budgeted and standard data for productivity include the following Direct labour Ten employees work for 45 hour a week. The standard rate of pay


The budgeted and standard data for productivity include the following


Direct labour
Ten employees work for 45 hour a week. The standard rate of pay is ksh 4 per hour. Output per hour is 40 kg of the product.


Direct material
Material          quantity kg       price per kg
X                          60                   2.00
Y                         40                     1.00
Z                        100                    1.40
From this standard matrix 180 kg of product is expected
Actual data for first week in April were as follows
Hours worked    45
Rate of pay ksh 4 per hour
Overhead incurredksh 5400
Output1980 kg
Production and consumption of materials were as follows:
Material     Quantity (kg)
X                  700
Y                   440
Z                  1120

Required
(a)Calculate the following direct material variance for each material (10mks)
i.Total
ii. Price
iii. Usage
iv. mix
(b)Calculate the direct labor efficiency variance (10mks)

Step by Step Solution

3.31 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Part A 1 Direct material total variance will be 100 favorable ii Direct material price variance ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!