Question: Question 3 0 / 1 point Activity Predecessor Optimistic Most-Likely Pessimistic 7 9 | A | | B,C B.C | DE | ( Given the

Question 3 0 / 1 point Activity Predecessor

Question 3 0 / 1 point Activity Predecessor Optimistic Most-Likely Pessimistic 7 9 | A | | B,C B.C | DE | ( Given the estimated activity times, what is the probability that the project will be completed within 22 days? 16% 50% 84% 93% It isn't possible to determine given this information