Question: Question 3 0 ( 1 point ) You're the project manager for a highway construction project. The superv your building team alerts you to a
Question point
You're the project manager for a highway construction project. The superv your building team alerts you to a problem found with one of the pylons orang warning cones You use an Ishikawa diagram to try to figure out the root cause of the defect. What process is being performed?
Page :
Quality Management
Quality Control
Quality planning
Quality Assurance
Page :
Page