Question: Question 3 [ 1 5 Marks ] Consider a project that involves making 1 0 similar dinner tables over 1 0 weeks for a Total
Question
Marks
Consider a project that involves making similar dinner tables over weeks for a Total Budgeted Cost TBC of $ This translates to $ per dinner table and one table per week. At the end of week you determine that $ has been spent and tables have been made.
Determine the following:
What is the earned value at week
What is the cost variance at week
What is the cost performance index of this project at week
Calculate the forecasted cost at completion at week
Is the project forecasted to overrun the or underrun the budget at completion?