Question: QUESTION 3 1 Consider the following work breakdown structure: table [ [ , table [ [ Start ] , [ Activity ] ]

QUESTION 31
Consider the following work breakdown structure:
\table[[,\table[[Start],[Activity]],\table[[Finish],[Node]],Duration Estimate (Days)],[A,1,2,9,15,21],[B,1,3,13,21,23],[C,2,4,6,9,18],[D,2,5,23,35,47],[E,3,5,19,26,27],[F,4,6,23,29,41],[G,5,6,14,20,26],[H,6,7,2,5,8]]
What is the probability that the critical path for this project will be completed within 75 weeks? (Please use decimal point format.)
 QUESTION 31 Consider the following work breakdown structure: \table[[,\table[[Start],[Activity]],\table[[Finish],[Node]],Duration Estimate (Days)],[A,1,2,9,15,21],[B,1,3,13,21,23],[C,2,4,6,9,18],[D,2,5,23,35,47],[E,3,5,19,26,27],[F,4,6,23,29,41],[G,5,6,14,20,26],[H,6,7,2,5,8]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!