Question: QUESTION 17 Consider the following work breakdown structure: Time Estimates (days) Activity Start Precedes Optimistic Most Likely Pessimistic AB End End What is the estimated

QUESTION 17 Consider the following work breakdown
QUESTION 17 Consider the following work breakdown structure: Time Estimates (days) Activity Start Precedes Optimistic Most Likely Pessimistic AB End End What is the estimated expected (mean) time for project completion? 201 days 380 days 143 days 189 days 191 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!