Question: Pessimistic V 40 QUESTION 12 Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Start U.V U w 35 50

Pessimistic V 40 QUESTION 12 Consider the
Pessimistic V 40 QUESTION 12 Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Start U.V U w 35 50 W.X 28 w z 26 35 Y 28 40 Y z 26 Z End 36 60 What is the estimated slack time for activity W? 45 days 85 days 25 days O days 35 days 65 52 44 52 38 84 29