Question: Question 3 ( 1 point ) The critical path in a project network is the: a shortest path through the network. b network path using

Question 3(1 point)
The critical path in a project network is the:
a shortest path through the network.
b network path using the most resources.
c longest path through the network.
d network path with the most difficult activities.
 Question 3(1 point) The critical path in a project network is