Question: Question 3 1.5 points Save Answer In below CPM diagram, If activity D is crashed by 4 days, how many days the project duration will

Question 3 1.5 points Save Answer In below CPM

Question 3 1.5 points Save Answer In below CPM diagram, If activity D is crashed by 4 days, how many days the project duration will be delayed? 1 5 5 19 7 25 A D 2 1 6 23 4 29 7 12 18 30 33 F END START 7 0 18 30 o 33 1 6 6 19 11 29 B 1 0 19 0 29 7 0 31