Question: QUESTION 3 4 Consider the following work breakdown structure: table [ [ , table [ [ Start ] , [ Activity ] ]
QUESTION
Consider the following work breakdown structure:
tabletableStartActivitytableFinishNodeDuration Estimate DaysNodeOptimistic,Most Likely,Pessimistic,,ABCDEFGH
Within what amount of time in weeks is there a percent probability that the critical path for this project will be
Within what amount of time in weeks is there a percent probability that the critical path for this project will be
completed? Please keep digits after the decimal point.
completed? Please keep digits after the decimal point.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
