Question: Question 3 5 ( 0 . 7 5 points ) Based on the information provided, what is the slack time for activity E

Question 35(0.75 points)
Based on the information provided, what is the slack time for activity "E"?
\table[[Activity,Immediate Predecessor,Time in Days],[A,-,5],[B,-,2],[D,-,6],[E,B,4],[G,A,3],[H,E&D,5],[,C,4],[,F&G,6]]
0 days
1 day
4 days
2 days