Question: Question 3 6 ( 1 point ) In project scheduling, which of the following correctly calculates the early finish for an activity? Late Start +

Question 36(1 point)
In project scheduling, which of the following correctly calculates the early finish for an activity?
Late Start + time
Late Finish + time
Early Start + Slack
Early Start + time