Question: QUESTION 3 8 A project has four activities: A , B , C , and D . The budgeted ( planned ) cost of each

QUESTION 38
A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K,$14K,$12K, and $28K, respectively. The planned percentages complete for the current date are 90%,80%,70%, and 20% respectively. The actual percentages complete for the current date are 100%,90%,75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for the project?
$0- $15K
Over $60K
$15.01K-$30K
$40.01K-$45K
$45.01K-$60K