Question: Question 3 8 In crashing a project, a manager will generally focus on the activities which are on the critical path and are the least

Question 38
In crashing a project, a manager will generally focus on the activities which
are on the critical path and are the least costly to crash.
are the easiest to crash
are the least costly to crash.
are not on the critical path