Question: Question 3 a) Reproduce the network chart below in your answer books and complete it. note: all time are in weeks. D 5 B (8

 Question 3 a) Reproduce the network chart below in your answer

Question 3 a) Reproduce the network chart below in your answer books and complete it. note: all time are in weeks. D 5 B (8 marks) b) Identify project duration (2 marks) c) Identify total float for each activity - you must show working to gain marks. (8 marks) d) Identify the Critical Path (2 marks) e) Construct a GANTT chart for the project, (including slack time for each activity)