Question: Question 3: An engineering workshop which fabricates window frames has set a target to complete 200 frames every month in 2022. The following data from

Question 3: An engineering workshop which

Question 3: An engineering workshop which fabricates window frames has set a target to complete 200 frames every month in 2022. The following data from the last 18 months is available. Plot a Z-chart to help the manager of the workshop track the fabrication progress at the end of June 2022. Month Number completed Number completed (2021) (2022) January 150 190 February 160 185 March 180 200 April 220 235 May 140 130 June 140 160 July 150 August 170 September 190 October 190 November 200 December 120