Question: Question 3 Create a work breakdown structure (WBS) of the following key activities for redesigning Nando's restaurant nts and updating its branding Use the bullet
Question 3 Create a work breakdown structure (WBS) of the following key activities for redesigning Nando's restaurant nts and updating its branding
Use the bullet points below to create the WES
Conduct research on customer preferences and market trends (2 months)
Define project scope and objectives (2 months) . Assemble project team with expertise in design, architecture, and branding (1 month).
Develop a detailed project plan with timelines and milestones (5 months) .
Collaborate with franchisees, suppliers, and employees to ensure buy-in and support (1 month) Finalise design and branding elements (2 months) Implement new design in pilot locations (2 months).
Conduct testing and evaluation of new design in pilot locations (1 month) .
Refine design, and branding elements based on pilot testing (2 months)
Develop an implementation plan for rolling out the new design across multiple locations (2 months) Provide training and support to franchisees and employees (2 months) .
Implement new design in all locations (1 month) Conduct post-implementation review and evaluation (2 months) (15)
3.2 Based on the WBS in 3.1, create a Gantt chart. (15)