Question: Question 3 Progress reports do not have to be distributed weekly. Depending on the project, it may be preferable to distribute reports which cover a

Question 3
Progress reports do not have to be distributed weekly. Depending on the project, it may be preferable to distribute reports which cover a longer time period such as a month or a quarter.
True
False
 Question 3 Progress reports do not have to be distributed weekly.