Question: Question 3 : Project Scheduling [ 2 2 marks ] Consider the following project schedule table [ [ Activity ID , Predecessor,Duration ( weeks
Question : Project Scheduling
marks
Consider the following project schedule
tableActivity IDPredecessor,Duration weeksANONE,BNONE,CNONE,DCEBFBGFHAIDEG
a Draw a Gantt chart for the above project schedule.
b Draw a PERT diagram for the above project schedule.
c What is the earliest completion time for the project? What is the Slack Time of each task? What is the critical path of the project?
d What would happen to the project if task F was delayed by weeks?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
