Question: Question 3 : Project Scheduling [ 2 2 marks ] Consider the following project schedule table [ [ Activity ID , Predecessor,Duration ( weeks

Question 3: Project Scheduling
[22 marks]
Consider the following project schedule
\table[[Activity ID,Predecessor,Duration (weeks)],[A,NONE,3],[B,NONE,7],[C,NONE,6],[D,C,5],[E,B,9],[F,B,5],[G,F,7],[H,A,4],[I,D,E,G,8]]
(a) Draw a Gantt chart for the above project schedule.
[4]
(b) Draw a PERT diagram for the above project schedule.
[4]
(c) What is the earliest completion time for the project? What is the Slack Time of each task? What is the critical path of the project?
[12]
(d) What would happen to the project if task F was delayed by 3 weeks?
[2]
 Question 3: Project Scheduling [22 marks] Consider the following project schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!