Question: QUESTION 3 table [ [ Activity , Normal time in Days,Normal cost in $ , Crash time in Days, table [ [ Crash

QUESTION 3
\table[[Activity,Normal time in Days,Normal cost in $,Crash time in Days,\table[[Crash cost in $ per],[Day]]],[A,3,600,2,450],[B,1,50,-,],[C,5,3000,3,600],[D,2,2000,-,],[E,4,1200,2,300],[F,1,300,-,],[G,4,1600,2,250],[H,10,4000,2,200],[J,2,800,-,],[K,4,2200,3,150]]
(Note: Read the table in the following manner: activity A can be compressed by one day from three days to two days, etc)
You are required to compress the schedule TWICE and determine the outcomes of each compression.
 QUESTION 3 \table[[Activity,Normal time in Days,Normal cost in $,Crash time in