Question: Question 3: Use the activity table below and execute the following: Develop a ES schedule with slack Activity Predecessor Duration Resources per day A Start
Question 3: Use the activity table below and execute the following:
Develop a ES schedule with slack
| Activity | Predecessor | Duration | Resources per day |
| A | Start | 4 | 36 |
| B | A | 6 | 30 |
| C | A | 8 | 45 |
| D | A | 5 | 20 |
| E | B | 6 | 15 |
| F | B,C | 8 | 25 |
| G | D | 3 | 12 |
| H | E | 8 | 22 |
| I | F | 5 | 32 |
| J | C,G | 5 | 25 |
| K | I | 8 | 20 |
| L | J,K | 6 | 28 |
| M | H,L | 4 | 30 |