Question: Question 4: Use the activity table below and execute the following: Populate an Activity table Activity Predecessor Duration Resources per day A Start 36 4

Question 4: Use the activity table below and execute the following:

Populate an Activity table

Activity

Predecessor

Duration

Resources per day

A

Start

36

4

B

A

30

6

C

A

45

8

D

A

20

5

E

B

15

6

F

B,C

25

8

G

D

12

3

H

E

22

8

I

F

32

5

J

C,G

25

5

K

I

20

8

L

J,K

28

6

M

H,L

30

4